Data Center Building Automation System Replacement

Size

Sq. Ft.

Location

Irving

Owner

Cushman & Wakefield, Inc.

Client

CCLLC was tasked with commissioning a complete systems BAS upgrade of mission critical data center facilities. The controls systems swapped out the existing Johnson Controls to a Siemens controls system with security criteria necessary for federal compliance. The controls system upgrade included power generation systems, central plant chillers and cooling towers, Air-Handling Units, CRAHs, terminal units, and all of the ancillary support equipment including sensors, control devices, and pumps to support their operation.
This project included multiple phases through conceptual design to construction and commissioning requiring coordination of various team members across the state and nation to meet the scheduling deadlines and manpower requirements.